Substation Scout

APS request Q306

APS queue ID Q306

Queue request Q306 was listed in the APS interconnection queue at the end of 2025 as a 18 MW battery project in Maricopa County, AZ, according to Berkeley Lab’s queue data file. The filing names Gila Bend as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of May 1, 2022.

Queue IDQ306
Project nameNot reported
Status (as published)Operational
SubstationGila Bend
Point of interconnectionGila Bend 12kV
CountyMaricopa
StateAZ
Voltage12 kV
Capacity18 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2022-05-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Gila Bend substation: 3 requests in the APS queue, 2 active totaling 36 MW.

Queue IDProjectMWResourceStatus
Q307Not reported18BatteryOperational
Q76Not reported20SolarWithdrawn

Maricopa, AZ: 259 requests in the APS queue, 82 active totaling 24,048 MW.

Tracked changes

Not tracked. APS rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityArizona Public Service
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)In-Service
Queue date2019-04-24

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first