Home / TVA / Substations / Johnsonville Fossil Plant - Yard
Johnsonville Fossil Plant - Yard substation interconnection queue
2 active projects
totaling 674 MW in the TVA queue.
2 TVA queue filings name Johnsonville Fossil Plant - Yard as the point of interconnection, all in Humphreys County, TN.
2 active projects
674 active MW
2 total filed
Queue ID Project kV MW Resource Status
401
Not reported
161
593
Gas
Active
426
Not reported
161
81
Gas
Active
A request with terminal status left the queue as filed.
That is a record of the filing, not evidence of injection capacity at this location.
Confirm deliverability with TVA before relying on these figures.
Site Scanner draws on HIFLD substations and electric retail service
territories, newer substations HIFLD lacks from OpenStreetMap, EIA gas transmission pipelines, HIFLD gas facilities and gas
utility territories, USGS watershed boundaries, FEMA flood hazard layers and US Census
geocoding. Queue data is compiled from public interconnection
queue filings. Every figure carries its source and retrieval date.
A withdrawal records that a request left the queue. It says
nothing about injection capacity at that location. Verify with the relevant ISO before
relying on any figure. Queue datasets are tracked separately and are
not directly comparable: status vocabularies, fuel coding, and publication
cadence all differ.
Screening aid only. Not a system impact study. Contiguous US.