TVA request 80
TVA queue ID 80
Queue request 80 was listed in the TVA interconnection queue at the end of 2025 as a 900 MW project in Benton County, MS, according to Berkeley Lab’s queue data file. Its status as of December 31, 2025 was “Operational”.
| Queue ID | 80 |
|---|---|
| Project name | Not reported |
| Status (as published) | Operational |
| Substation | Not reported |
| Point of interconnection | Not reported |
| County | Benton |
| State | MS |
| Voltage | Not reported |
| Capacity | 900 MW |
| Resource (as published) | Other |
| Resource category | Other (normalized for filtering) |
| Proposed online date | Not reported |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Benton, MS: 4 requests in the TVA queue, 4 active totaling 1,139 MW.
Tracked changes
Not tracked. TVA rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | Tennessee Valley Authority |
|---|---|
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | IA Executed |
| Queue date | 2000-01-18 |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.