Substation Scout

TVA request 658

TVA queue ID 658

Queue request 658 was listed in the TVA interconnection queue at the end of 2025 as a 3 MW hydro project in Loudon County, TN, according to Berkeley Lab’s queue data file. The filing names Ft. Loudon Hydro Bus as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of February 1, 2028.

Queue ID658
Project nameNot reported
Status (as published)Active
SubstationFt. Loudon Hydro Bus
Point of interconnectionFt. Loudon Hydro Bus 364422
CountyLoudon
StateTN
VoltageNot reported
Capacity3 MW
Resource (as published)Hydro
Resource categoryHydro (normalized for filtering)
Proposed online date2028-02-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Ft. Loudon Hydro Bus substation: 2 requests in the TVA queue, 2 active totaling 7 MW.

Queue IDProjectMWResourceStatus
659Not reported4HydroActive

Loudon, TN: 4 requests in the TVA queue, 4 active totaling 49 MW.

Tracked changes

Not tracked. TVA rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityTennessee Valley Authority
ClusterTC25-055
Project typeUpgrade
Study phase (standardized by Berkeley Lab)Cluster Study
Queue date2024-10-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.