Whitfield, GA interconnection queue

1 active project totaling 640 MW in the TVA queue, plus 1 with terminal status (shown grayed).

1active projects
640active MW
2total filed
Queue IDProjectkVMWResourceStatus
62 Not reported n/r 640 Other Operational
163 Not reported n/r 581 Other Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with TVA before relying on these figures.