Substation Scout

Simpson, KY interconnection queue

1 active project totaling 69 MW in the TVA queue, plus 1 with terminal status (shown grayed).

1active projects
69active MW
2total filed
Queue IDProjectkVMWResourceStatus
360 Not reported n/r 200 Solar Withdrawn
388 Not reported n/r 69 Solar Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with TVA before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first