1 active project totaling 100 MW in the TVA queue, plus 4 with terminal status (shown grayed).

1active projects
100active MW
5total filed
Queue IDProjectkVMWResourceStatus
78 Not reported n/r 235 Other Withdrawn
474 Not reported n/r 180 Hybrid Withdrawn
375 Not reported n/r 164 Solar Withdrawn
342 Not reported n/r 100 Solar Operational
366 Not reported n/r 58 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with TVA before relying on these figures.