Substation Scout

Murray, GA interconnection queue

1 active project totaling 50 MW in the TVA queue, plus 1 with terminal status (shown grayed).

1active projects
50active MW
2total filed
Queue IDProjectkVMWResourceStatus
308 Not reported n/r 50 Solar Withdrawn
309 Not reported n/r 50 Gas Operational

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with TVA before relying on these figures.