Substation Scout

Mcminn, TN interconnection queue

1 active project totaling 68 MW in the TVA queue, plus 2 with terminal status (shown grayed).

1active projects
68active MW
3total filed
Queue IDProjectkVMWResourceStatus
439 Not reported n/r 200 Solar Withdrawn
668 Not reported n/r 90 Solar Withdrawn
25RSC-003 Not reported 161 68 Solar Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with TVA before relying on these figures.