Substation Scout

Cherokee, NC interconnection queue

1 active project totaling 42 MW in the TVA queue.

1active projects
42active MW
1total filed
Queue IDProjectkVMWResourceStatus
46 Not reported n/r 42 Other Operational

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with TVA before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first