West Point

Named in 3 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).

—county (not printed)
—kV in the quote
GPCproject sponsor
3projects in the plan

The plan prints no county for this substation, and no utility project page found names one for it.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
PITTMAN RD - WEST POINT (APC) 115kV REBUILD
Rebuild 4.3 miles of the Pittman Road - West Point (APC) 115kV line with 200C 1351 ACSS conductor. Replace the bus and associated jumpers at West Point #2 with higher rated bus work and jumpers.
TEAMS 13040 · plan p.282 · zone 213
GPC In the plan
p.21
Jun 1, 2031 New project Pittman Rd, Pittman Road, West Point
BARTLETTS FERRY 1-4 REPLACEMENT SUB
Replace the jumpers at Bartletts Ferry, on the Bartletts Ferry - West Point (APC) 115kV line, with higher rated jumpers. Rebuild the substation to new configuration to accommodate existing 115kV lines and existing generation interconnection.
TEAMS 18979 · plan p.113 · zone 213
GPC In the plan
p.9
Dec 31, 2026 New project Bartletts Ferry, REPLACEMENT, West Point
BARTLETTS FERRY - BACKWATER TAP 115kV REBUILD
Rebuild the Bartlett's Ferry - Backwater Tap section of the Bartletts Ferry - West Point (APC) 115kV line with 200C 1351 AAC conductor. Replace switch with higher rated switch.
TEAMS 21287 · plan p.153 · zone 213
GPC In the plan
p.12
Jun 1, 2028 New project BACKWATER, Bartletts Ferry, West Point

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.