WADLEY

Named in 1 project in the 2025 GA ITS Ten-Year Plan (2026-2035).

—county (not printed)
—kV in the quote
GPCproject sponsor
1projects in the plan

The plan prints no county for this substation, and no utility project page found names one for it.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
HATCH - WADLEY 500 kV LINE STRATEGIC PROJECT
Construct a new 500kV line from Hatch - Wadley Primary with (3) 100C 1113 ACSR conductor.
TEAMS 20756 · plan p.279 · zone 215
GPC In the plan
p.21
Jun 1, 2031 No change HATCH, WADLEY

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.