TRUMAN PARKWAY
Named in 1 project in the 2025 GA ITS Ten-Year Plan (2026-2035).
—county (not printed)
—kV in the quote
SAVproject sponsor
1projects in the plan
The plan prints no county for this substation, and no utility project page found names one for it.
Projects naming this substation
As the plan prints them. The sponsor is the project’s; one project can split work between owners.
| Project | Sponsor | Where in the plan | Need date | Change from the previous plan | Substations named |
|---|---|---|---|---|---|
| SAV: BOULEVARD - MAGNOLIA - TRUMAN PARKWAY 115kV REBUILDS Rebuild 3 miles of the Magnolia - Truman Parkway with 200C 1351 ACSS Martin conductor. Upgrade switches at Magnolia substation to a higher rating switches and jumpers at Truman Parkway. Rebuild the entire Boulevard to Magnolia 115kV line, approx. 4.56 miles with 200C 1351 ACSS Martin or higher rated conductor. At Magnolia, replace a switch with a higher rating. TEAMS 20407 · plan p.219 · zone 219 |
SAV | In the plan p.17 |
Jun 1, 2029 | Delayed from 2028 to 2029 | Magnolia, TRUMAN PARKWAY |
Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.
Before relying on any of this
- The plan prints no county for a substation. A county shown here is printed in the plan beside the station, or on a Georgia Power or Georgia Transmission project page that names the same station and one county.
- Project Sponsor belongs to the project, not to each station; one project can split work between owners.
- Costs are redacted in the public version of the plan and are not shown.