Thumbs Up
Named in 1 project in the 2025 GA ITS Ten-Year Plan (2026-2035).
—county (not printed)
—kV in the quote
GTCproject sponsor
1projects in the plan
The plan prints no county for this substation, and no utility project page found names one for it.
Projects naming this substation
As the plan prints them. The sponsor is the project’s; one project can split work between owners.
| Project | Sponsor | Where in the plan | Need date | Change from the previous plan | Substations named |
|---|---|---|---|---|---|
| GTC: MORNING HORNET - STANTON SPRINGS 115kV Add a second 230/115kV auto transformer at Morning Hornet substation. Also, build a new 115kV line from Morning Hornet to Stanton Springs approximately 2.4 miles, with 100C 1351 ACSR conductor. GPC: Rebuild 0.1-mile segment of the Stanton Springs - Thumbs Up 115kV line with 200C 795 ACSS. TEAMS 20015 · plan p.133 · zone 212 |
GTC | In the plan p.11 |
Jun 1, 2027 | Delayed from 2026 to 2027 | Morning Hornet, Stanton Springs, Thumbs Up |
Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.
Before relying on any of this
- The plan prints no county for a substation. A county shown here is printed in the plan beside the station, or on a Georgia Power or Georgia Transmission project page that names the same station and one county.
- Project Sponsor belongs to the project, not to each station; one project can split work between owners.
- Costs are redacted in the public version of the plan and are not shown.