Shoal Creek

Named in 3 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).

—county (not printed)
—kV in the quote
GPC, GTCproject sponsor
3projects in the plan

The plan prints no county for this substation, and no utility project page found names one for it.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
MCEVER ROAD - SHOAL CREEK 115kV REBUILD
Rebuild approximately 3.05 miles of the McEver Road - Shoal Creek 115kV line with 200C 1351 ACSS conductor using 200C 1351 ACSS conductor.
TEAMS 19621 · plan p.214 · zone 212
GPC In the plan
p.16
Jun 1, 2029 No change McEver Road, Shoal Creek
GTC: SHOAL CREEK - SOUTH HALL 230kV REBUILD
Rebuild approximately 7.9 miles of the Shoal Creek - South Hall 230kV line. Upgrade limiting elements on the line with 200C 1351 ACSS conductor.
TEAMS 20791 · plan p.295 · zone 212
GTC In the plan
p.22
Jun 1, 2033 No change Shoal Creek, South Hall
MCEVER ROAD - SHOAL CREEK 115kV REBUILD
Rebuild approximately 2.9 miles of the McEver Road - Shoal Creek 115kV line, using 200C 1351 ACSS conductor.
TEAMS 21053 · plan p.296 · zone 212
GPC In the plan
p.22
Jun 1, 2033 No change McEver Road, Shoal Creek

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.