Scottdale
Named in 2 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).
—county (not printed)
—kV in the quote
GPCproject sponsor
2projects in the plan
The plan prints no county for this substation, and no utility project page found names one for it.
Projects naming this substation
As the plan prints them. The sponsor is the project’s; one project can split work between owners.
| Project | Sponsor | Where in the plan | Need date | Change from the previous plan | Substations named |
|---|---|---|---|---|---|
| SCOTTDALE RELAY MODERNIZATION Upgrade protection on 230kV bus and 230/115kV auto transformers at the Scottdale station. Add adequate monitoring on DC supply. TEAMS 20489 · plan p.54 · zone 206 |
GPC | In the plan p.9 |
Jun 1, 2026 | No Change | Scottdale |
| DECATUR - SCOTTDALE 115kV LINE JUMPER REPLACEMENT Replace the limiting jumper along the Decatur - Scottdale 115kV line with higher rated jumper. TEAMS 21295 · plan p.305 · zone 206 |
GPC | In the plan p.22 |
Jun 1, 2035 | New project | Decatur, Scottdale |
Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.
Before relying on any of this
- The plan prints no county for a substation. A county shown here is printed in the plan beside the station, or on a Georgia Power or Georgia Transmission project page that names the same station and one county.
- Project Sponsor belongs to the project, not to each station; one project can split work between owners.
- Costs are redacted in the public version of the plan and are not shown.
Site Scanner