Mink Creek
Named in 1 project in the 2025 GA ITS Ten-Year Plan (2026-2035).
—county (not printed)
500kV in the quote
GTCproject sponsor
1projects in the plan
Described as new. The quoted wording calls this substation new. “new 500kV Mink Creek substation” — TEAMS 21077, plan p.252
The plan prints no county for this substation, and no utility project page found names one for it.
Projects naming this substation
As the plan prints them. The sponsor is the project’s; one project can split work between owners.
| Project | Sponsor | Where in the plan | Need date | Change from the previous plan | Substations named |
|---|---|---|---|---|---|
| GTC: ROCKVILLE -MINK CREEK -WARTHEN 500KV LINES Build the new 500kV line from Rockville to Mink Creek and Mink Creek to Warthen, approximately 20 miles and 9 miles long respectively with 100C (3) 1113 ACSR Bluejay conductor. Build the new 500kV Mink Creek substation. Make all necessary accommodations at Warthen and Rockville for the new 500kV breakers. TEAMS 21077 · plan p.252 · zone 214 |
GTC | In the plan p.19 |
Jun 1, 2030 | No change | Mink Creek |
Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.
Before relying on any of this
- The plan prints no county for a substation. A county shown here is printed in the plan beside the station, or on a Georgia Power or Georgia Transmission project page that names the same station and one county.
- Project Sponsor belongs to the project, not to each station; one project can split work between owners.
- Costs are redacted in the public version of the plan and are not shown.