Klondike

Named in 2 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).

—county (not printed)
—kV in the quote
GPCproject sponsor
2projects in the plan

The plan prints no county for this substation, and no utility project page found names one for it.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
KLONDIKE RELAY MODERNIZATION
Upgrade protection on 230kV buses at the Klondike station. Add adequate monitoring on DC supply.
TEAMS 20490 · plan p.52 · zone 206
GPC In the plan
p.8
Jun 1, 2026 No Change Klondike
CONYERS - KLONDIKE 230kV SECOND LINE
Build a new 7.2 miles line from Conyers to Klondike with 200C (2) 1351 ACSS Martin conductor. Build one new 230kV breaker terminal at Conyers and one new 230kV terminal at Klondike.
TEAMS 21142 · plan p.194 · zone 206
GPC In the plan
p.15
Jun 1, 2029 No change Conyers, Klondike

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.