Named in 2 projects in the 2025 GA ITS Ten-Year Plan (2026-2035), plus 1 on its cancelled or completed lists.

—county (not printed)
—kV in the quote
GPCproject sponsor
2projects in the plan

The plan prints no county for this substation, and no utility project page found names one for it.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
JESUP - WEST BRUNSWICK 115 kV REBUILD
Rebuild the Jesup - West Brunswick 115kV line, approximately 31.44 miles, with 100C 795 ACSR conductor.
TEAMS 18624 · plan p.152 · zone 218
GPC In the plan
p.12
Dec 31, 2027 New project Jesup, West Brunswick
JESUP - OFFERMAN 115kV REBUILD
Rebuild approximately 20 miles of the Jesup - Offerman 115kV line with 100C 795 ACSR Drake conductor.
TEAMS 18668 · plan p.137 · zone 218
GPC In the plan
p.11
Jun 1, 2027 No change Jesup, Offerman

On the cancelled or completed lists

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
JESUP - LUDOWICI PRIMARY 115kV REBUILD
TEAMS 11821 · zone 218
Not printed Completed list
p.26
Jun 1, 2025
as listed
— Jesup, LUDOWICI PRIMARY

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.