Substation Scout

First Avenue

Named in 1 project in the 2025 GA ITS Ten-Year Plan (2026-2035).

—county (not printed)
—kV in the quote
GPCproject sponsor
1projects in the plan

The plan prints no county for this substation, and no utility project page found names one for it.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
FIRST AVENUE - NORTH COLUMBUS 115kV LINE REBUILD
Rebuild 0.9 mile of the North Columbus - First Avenue 115kV line with 200C 1351 ACSS conductor.
TEAMS 13166 · plan p.188 · zone 213
GPC In the plan
p.14
Dec 1, 2028 No change First Avenue, North Columbus

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first