Named in 1 project in the 2025 GA ITS Ten-Year Plan (2026-2035).

—county (not printed)
—kV in the quote
Daltonproject sponsor
1projects in the plan

The plan prints no county for this substation, and no utility project page found names one for it.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
DU: EAST DALTON - OOSTANAULA 115kV REBUILD
Rebuild 7.4 miles of East Dalton - Oostanaula and Dalton - East Dalton 115kV double circuit lines between East Dalton substation and the Dalton substation frame with 200C 795 ACSS This project also rebuilds the Dalton - East Dalton 115kV line.
TEAMS 18679 · plan p.92 · zone 211
Dalton In the plan
p.7
Jun 1, 2026 No change Dalton, East Dalton, OOSTANAULA

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.