Dyer Road

Named in 3 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).

—county (not printed)
—kV in the quote
GPC, GTCproject sponsor
3projects in the plan

The plan prints no county for this substation, and no utility project page found names one for it.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
DYER ROAD - EAST ROANOKE 115kV REBUILD
Rebuild 20.7 miles from Dyer Road to Wansley tap on the Dyer Road - East Roanoke (APC) 115kV line with advanced conductor.
TEAMS 20024 · plan p.160 · zone 211
GPC In the plan
p.13
Jun 1, 2028 Delayed from 2027 to 2028 Dyer Road, East Roanoke
GTC: DYER ROAD - SOUTH COWETA 115kV REBUILD PHASE 1
Rebuild the 9.2 miles section on the Dyer Road - South Coweta 115kV line from Dyer Road to Madras with 200C 1351 ACSS Martin and replace limiting elements at Dyer Road and Madras.
TEAMS 21261 · plan p.248 · zone 208
GTC In the plan
p.18
Jun 1, 2030 New project Dyer Road, South Coweta
GTC: DYER ROAD - SOUTH COWETA 115kV REBUILD PHASE 2
Rebuild the 3.2 miles section on the Dyer Road - South Coweta 115kV line from South Coweta to Mcintosh Trail with 200C 1351 ACSS Martin and replace limiting elements at South Coweta and Mcintosh Trail.
TEAMS 21262 · plan p.287 · zone 208
GTC In the plan
p.21
Jun 1, 2032 New project Dyer Road, South Coweta

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.