Dawson Crossing

Named in 3 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).

—county (not printed)
—kV in the quote
Dalton, GTCproject sponsor
3projects in the plan

The plan prints no county for this substation, and no utility project page found names one for it.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
DU: DAWSON CROSSING - NELSON (WHITE) 115 kV REBUILD
Rebuild approximately 15.7 miles of the Dawson Crossing - Nelson (White) 115kV line with 200C 1351 ACSS Martin.
TEAMS 18669 · plan p.238 · zone 212
Dalton In the plan
p.18
Jun 1, 2030 No change Dawson Crossing, Nelson
GTC: DAWSON CROSSING - NELSON (BLACK) 115kV REBUILD
Rebuild approximately 7.5 miles from Nelson to McClain Mountain to Big Canoe on the Dawson Crossing - Nelson (Black) 115kV line.
TEAMS 21034 · plan p.207 · zone 211
GTC In the plan
p.16
Jun 1, 2029 New project Dawson Crossing, Nelson
GTC: CUMMING - DAWSON CROSSING 115kV LINE REBUILD
Rebuild approximately 12.7 miles of the Cumming - Dawson Crossing 115kV Line with 200C 1351 ACSS Martin conductor.
TEAMS 21291 · plan p.301 · zone 202
GTC In the plan
p.22
Jun 1, 2034 New project Cumming, Dawson Crossing

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.