Bay Creek
Named in 3 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).
—county (not printed)
—kV in the quote
GPC, GTCproject sponsor
3projects in the plan
The plan prints no county for this substation, and no utility project page found names one for it.
Projects naming this substation
As the plan prints them. The sponsor is the project’s; one project can split work between owners.
| Project | Sponsor | Where in the plan | Need date | Change from the previous plan | Substations named |
|---|---|---|---|---|---|
| GTC: BAY CREEK 230/115kV SECOND AUTO TRANSFORMER Install a second 230/115kV auto transformer at the Bay Creek substation. TEAMS 10814 · plan p.202 · zone 202 |
GTC | In the plan p.15 |
Jun 1, 2029 | No change | Bay Creek |
| BAY CREEK - CONYERS 230kV REBUILD Rebuild the Rockdale to Bay Creek segment, approximately 15.29 miles, of the Bay Creek - Conyers 230kV line using 200C 1351 ACSS Martin conductor. TEAMS 20248 · plan p.284 · zone 202 |
GPC | In the plan p.21 |
Dec 31, 2031 | Project delayed from 2029 to 2031 | Bay Creek, Conyers |
| BAY CREEK - CONYERS 230kV LIMITING ELEMENT REPLACEMENT Replace equipment such as jumpers, switches, and traps at the Bay Creek, Rockdale, and Conyers substations with higher rating equipment. TEAMS 20758 · plan p.289 · zone 202 |
GPC | In the plan p.21 |
Jun 1, 2033 | No change | Bay Creek, Conyers |
Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.
Before relying on any of this
- The plan prints no county for a substation. A county shown here is printed in the plan beside the station, or on a Georgia Power or Georgia Transmission project page that names the same station and one county.
- Project Sponsor belongs to the project, not to each station; one project can split work between owners.
- Costs are redacted in the public version of the plan and are not shown.
Site Scanner