Atkinson
Named in 2 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).
—county (not printed)
—kV in the quote
GPCproject sponsor
2projects in the plan
The plan prints no county for this substation, and no utility project page found names one for it.
Projects naming this substation
As the plan prints them. The sponsor is the project’s; one project can split work between owners.
| Project | Sponsor | Where in the plan | Need date | Change from the previous plan | Substations named |
|---|---|---|---|---|---|
| ATKINSON - TILFORD YARDS 115kV REBUILD Rebuild 1.2 miles of the Atkinson - Tilford Yards 115kV line with 200C 1351 ACSS Martin. TEAMS 20761 · plan p.266 · zone 201 |
GPC | In the plan p.20 |
Dec 1, 2030 | Delayed within 2030 | Atkinson, Tilford Yards |
| ATKINSON - NORTHSIDE DRIVE 115kV REBUILD Rebuild a portion of the Atkinson – Northside Dr. 115kV line, approximately 3.2 miles from Atkinson to Chattahoochee with 200C 1351 ACSS Martin. TEAMS 20764 · plan p.286 · zone 201 |
GPC | In the plan p.21 |
Jun 1, 2032 | Delayed from 2030 to 2032 | Atkinson, Northside Dr., NORTHSIDE DRIVE |
Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.
Before relying on any of this
- The plan prints no county for a substation. A county shown here is printed in the plan beside the station, or on a Georgia Power or Georgia Transmission project page that names the same station and one county.
- Project Sponsor belongs to the project, not to each station; one project can split work between owners.
- Costs are redacted in the public version of the plan and are not shown.