Substation Scout

Athena

Named in 2 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).

—county (not printed)
230kV in the quote
GPC, MEAGproject sponsor
2projects in the plan

Expansion at an existing substation: new or expanded yard. The quoted wording describes a new or expanded yard, bus, bay or station at this substation. “Expand Athena 230kV bus” — TEAMS 21118

The plan prints no county for this substation, and no utility project page found names one for it.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
ATHENA - EAST WATKINSVILLE 115 kV REBUILD
Rebuild approximately 8.47 miles of the Athena - East Watkinsville 115kV line with 100C ACSR 1033 conductor.
TEAMS 17977 · plan p.151 · zone 212
GPC In the plan
p.12
Dec 31, 2027 No change Athena, East Watkinsville
MEAG: ATHENA - WARRENTON 230kV CONVERSION
Reconductor, rebuild, and convert as necessary the 115kV lines from Athena - Union Point - Ray Place Road - Warrenton Primary to 230kV operation. Expand Athena 230kV bus for new line termination, construct 230kV bus at Union Point, and expand 230kV bus at Warrenton Primary for new line termination. Install 230/115kV auto transformers at Union Point Primary and Ray Place Road. Replace limiting network equipment at sub…
TEAMS 21118 · plan p.260 · zone 215
MEAG In the plan
p.19
Jun 1, 2030 No change Athena, WARRENTON

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.