Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Wilson County. First named in the release with data as of June 1, 2021.

Wilsoncounty as printed
138kV
GVECutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Wilson, TX: ERCOT queue, 15 active of 18. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
GVEC Kicaster Substation Addition (formerly Wilson South)
Add a new load-serving substation 4.35 miles south of La Vernia along FM 775 with a 40 MVA PWT.
ERCOT project 61444
GVEC
Tier 4
Planned
Current-year planned tab
138 Oct 2026 Wilson South
Wilson County
Wilson South

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202661444Projected in-service dateSep 2026 → Oct 2026
February 1, 202661444Moved between tabsFuture → Current-year planned
February 1, 202661444Projected in-service dateAug 2026 → Sep 2026
February 1, 202561444Projected in-service dateOct 2026 → Aug 2026
October 1, 202461444Projected in-service dateApr 2026 → Oct 2026

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.