Substation Scout

Ursidae

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Wharton County. First named in the release with data as of February 1, 2025.

Whartoncounty as printed
138kV
AEP TCCutility
1projects listed

Described as new. The quoted wording calls this substation new. “Ursidae: Construct New 138 kV Station” — project 90055 title, as the utility reported it

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Wharton, TX: ERCOT queue, 42 active of 44. Same county, not the same substation.

Location

Wharton County, TX

County only. A source prints the county; no point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.

Sources: ERCOT Transmission Project and Information Tracking (TPIT) workbook, project(s) 90055 (release 2026-10-01). Researched by Substation Scout; checked November 21, 2026.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Ursidae: Construct New 138 kV Station
Interconnect Northington Solar to the new Ursidae 138 kV station on the El Campo to Victoria 138 kV line between Corichi and El Campo
ERCOT project 90055 · utility no. TP2024151
AEP TCC
Tier 4
Planned
Future tab
138 Jun 2027 Ursidae
Wharton County
Ursidae

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
February 1, 202590055First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.