Substation Scout

N. McCamey

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Upton County. First named in the release with data as of July 13, 2026.

Uptoncounty as printed
138kV
AEP TCC/LCRAutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Upton, TX: ERCOT queue, 18 active of 22. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
LCRA North McCamey Switch Station: Cap Bank Retirement
Retire the AEP Cap Banks at the LCRA's North McCamey Switch station
ERCOT project 109708 · utility no. TP2026117
AEP TCC/LCRA
Tier 4
Planned
Current-year planned tab
138 Jun 2026 N. McCamey
Upton County
N. McCamey

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 2026109708First listedon the Current-year planned tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.