Roanoke Switch
Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Tarrant County. First named in the release with data as of February 1, 2015.
No HIFLD substation record has this name in this county (a record of the same name exists in another county).
Generation interconnection requests filed in Tarrant, TX: ERCOT queue, 4 active of 4 · SPP queue, 0 active of 1. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Roanoke Area Upgrades Establish Roanoke_Exchange 138 kV Line ERCOT project 70900F · utility no. M5281 M5144 M5146 M5148 · RPG 22RPG003 |
ONCOR Tier 1 |
Under Construction Current-year planned tab |
345 | Dec 2026 | Roanoke Switch to Exchange Switch Tarrant County |
Roanoke Switch, Exchange Switch |
| FireHall_138kV_Switch Establish Fire Hall 138 kV Switch ERCOT project 72940 |
ONCOR Tier 4 |
Planned Future tab |
138 | Dec 2027 | Roanoke Switch to Kingsridge Switch Tarrant / Denton County |
Roanoke Switch, Kingsridge Switch |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 70900F | Status as reported | Planned → Under Construction |
| July 13, 2026 | 70900F | Projected in-service date | May 2026 → Dec 2026 |
| July 13, 2026 | 72940 | Moved between tabs | Current-year planned → Future |
| July 13, 2026 | 72940 | Projected in-service date | May 2026 → Dec 2027 |
| June 1, 2026 | 72940 | First listed | on the Current-year planned tab |
| February 1, 2026 | 70900F | Moved between tabs | Future → Current-year planned |
| October 1, 2024 | 70900F | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.