Dunham Switch
Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Tarrant County. First named in the release with data as of February 1, 2023.
Tarrantcounty as printed
345kV
ONCORutility
2projects listed
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Tarrant, TX: ERCOT queue, 4 active of 4 · SPP queue, 0 active of 1. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Roanoke Area Upgrades Dunham 345 kV Switch and Ramhorn 345 kV Switch ERCOT project 70900D · utility no. M5281 M5144 M5146 M5148 · RPG 22RPG003 |
ONCOR Tier 1 |
In-Service Completed tab |
345 | Dec 2025 actual 2025-12 |
Dunham Switch to Dunham Switch Tarrant County |
Dunham Switch |
| Roanoke Area Upgrades Ramhorn Hill – Dunham 345 kV Double-Circuit Line ERCOT project 70900E · utility no. M5281 M5144 M5146 M5148 · RPG 22RPG003 |
ONCOR Tier 1 |
In-Service Completed tab |
345 | Jun 2026 actual 2026-06 |
Dunham Switch to Ramhorn Switch Tarrant County |
Dunham Switch, Ramhorn Switch |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 70900E | Moved between tabs | Current-year planned → Completed |
| October 1, 2026 | 70900E | Status as reported | Planned → In-Service |
| July 13, 2026 | 70900E | Projected in-service date | Mar 2026 → Jun 2026 |
| June 1, 2026 | 70900D | Moved between tabs | Current-year planned → Completed |
| June 1, 2026 | 70900D | Status as reported | Planned → In-Service |
| February 1, 2026 | 70900E | Projected in-service date | Dec 2025 → Mar 2026 |
| June 1, 2025 | 70900D | Moved between tabs | Future → Current-year planned |
| June 1, 2025 | 70900E | Moved between tabs | Future → Current-year planned |
| October 1, 2024 | 70900E | Projected in-service date | May 2026 → Dec 2025 |
| June 1, 2024 | 70900E | Projected in-service date | Dec 2025 → May 2026 |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.