Montura
Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Starr County. First named in the release with data as of June 1, 2026.
Described as new. The quoted wording calls this substation new. “Montura: Construct New 345 kV Station” — project 103816 title, as the utility reported it
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Starr, TX: ERCOT queue, 21 active of 23. Same county, not the same substation.
Location
Starr County, TX
County only. A source prints the county; no point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.
How it was located: No point. TPIT puts Montura on the Cruce to Del Sol 345 kV line (ETT). Neither Cruce (a new station) nor Del Sol is named in OpenStreetMap, so the line is not bounded here. No document found describes the Montura site.
Sources: ERCOT TPIT, project(s) 103816 (release 39, 2026-10-01) · AEP Texas / ETT, Cruce - Del Sol Transmission Improvements Project page (2026). Researched by Substation Scout; checked November 21, 2026.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Montura: Construct New 345 kV Station Interconnect Bullring Wind 1, 2, and 3 to the new Montura 345 kV station on the Cruce to Del Sol 345 kV line ERCOT project 103816 · utility no. TP2025870 |
ETT Tier 4 |
Planned Future tab |
345 | Aug 2028 | Montura Starr County |
Montura |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 103816 | Projected in-service date | Jun 2028 → Aug 2028 |
| June 1, 2026 | 103816 | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.