Substation Scout

Taft

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in San Patricio County. First named in the release with data as of October 1, 2026.

San Patriciocounty as printed
69kV
AEP TCCutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in San Patricio, TX: ERCOT queue, 27 active of 28. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Taft: Rebuild Distribution Station
Rebuild the Taft distribution station
ERCOT project 103479 · utility no. DP25X0014
AEP TCC
Tier 4
Planned
Future tab
69 Dec 2030 Taft
San Patricio County
Taft

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 2026103479Projected in-service dateJun 2028 → Dec 2030
June 1, 2026103479First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.