Dupont PP1

Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in San Patricio County. First named in the release with data as of February 1, 2025.

San Patriciocounty as printed
138kV
AEP TCCutility
2projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in San Patricio, TX: ERCOT queue, 27 active of 28. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Dupont Switch to Dupont PP1 Circuit 1: Rebuild 138 kV Line
Rebuild the Dupont Switch to Dupont PP1 Circuit 1 138 kV line
ERCOT project 90016 · utility no. TP2024138
AEP TCC
Tier 4
Planned
Future tab
138 Nov 2028 Dupont Switch to Dupont PP1
San Patricio County
Dupont Switch, Dupont PP1
Dupont Switch to Dupont PP1 Circuit 2: Rebuild 138 kV Line
Rebuild the Dupont Switch to Dupont PP1 Circuit 2 138 kV line
ERCOT project 90029 · utility no. TP2024138
AEP TCC
Tier 4
Planned
Future tab
138 Nov 2028 Dupont Switch to Dupont PP1
San Patricio County
Dupont Switch, Dupont PP1

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
February 1, 202690016Projected in-service dateJun 2028 → Nov 2028
February 1, 202690029Projected in-service dateJun 2028 → Nov 2028
February 1, 202590016First listedon the Future tab
February 1, 202590029First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.