Named in 1 listed project in ERCOT’s transmission project tracking workbook, in San Patricio County. First named in the release with data as of February 1, 2017.

San Patriciocounty as printed
69kV
AEP TCCutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in San Patricio, TX: ERCOT queue, 27 active of 28. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Aransas Pass to Rincon: Rebuild 69 kV Line
Rebuild the Aransas Pass to Gregory to Rincon 69 kV line
ERCOT project 70675 · utility no. TP2022132 · RPG 24RPG035
AEP TCC
Tier 2
Planned
Future tab
69 Jan 2028 Aransas Pass to Rincon
San Patricio County
Aransas Pass, Rincon

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
June 1, 202670675Projected in-service dateOct 2027 → Jan 2028
February 1, 202670675Projected in-service dateJan 2027 → Oct 2027
June 1, 202570675Projected in-service dateDec 2027 → Jan 2027
February 1, 202570675Projected in-service dateJun 2026 → Dec 2027

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first