Tungsten

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Refugio County. First named in the release with data as of June 1, 2026.

Refugiocounty as printed
138kV
AEP TCCutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Refugio, TX: ERCOT queue, 1 active of 4. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Rincon to Tungsten: Rebuild 138 kV Line
Rebuild the Rincon to Tungsten 138 kV line
ERCOT project 104084 · utility no. TP2026007
AEP TCC
Tier 3
Planned
Future tab
138 Jun 2029 Rincon to Tungsten
Calhoun / Refugio County
Rincon, Tungsten

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 2026104084Projected in-service dateNov 2028 → Jun 2029
June 1, 2026104084First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.