Substation Scout

Refugio

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Refugio County. First named in the release with data as of February 1, 2015.

Refugiocounty as printed
69kV
AEP TCCutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Refugio, TX: ERCOT queue, 1 active of 4. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Refugio 138/69 kV:Install Capacitor Bank
Install 17.2 Mvar cap bank at the Refugio 69 kV station
ERCOT project 104617
AEP TCC
Tier 4
Planned
Future tab
69 Sep 2027 Refugio
Refugio County
Refugio

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
June 1, 2026104617First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.