Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Reagan County. First named in the release with data as of February 1, 2016.

Reagancounty as printed
69kV
AEP TNCutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Reagan, TX: ERCOT queue, 3 active of 3 · SPP queue, 0 active of 1. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Bison to Lightyear: Rebuild 69 kV Line
Rehab the Bison to Lightyear 69 kV line
ERCOT project 55470 · utility no. 1863
AEP TNC
Tier 4
Planned
Future tab
69 Nov 2028 Bison to Lightyear
Reagan / Crockett County
Bison, Lightyear

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
June 1, 202455470Projected in-service dateNov 2027 → Nov 2028

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first