Notus Switch

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Navarro County. First named in the release with data as of October 1, 2024.

Navarrocounty as printed
345kV
ONCORutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Navarro, TX: ERCOT queue, 26 active of 29. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Establish Notus 345 kV Switch
ERCOT project 87804 · utility no. R6371
ONCOR
Tier 4
Planned
Current-year planned tab
345 Dec 2026 Notus Switch to Notus Switch
Navarro County
Notus Switch

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
June 1, 202687804Projected in-service dateMay 2026 → Dec 2026
February 1, 202687804Moved between tabsFuture → Current-year planned
October 1, 202487804First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.