Ranger Camp 345
Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Mitchell County. First named in the release with data as of February 1, 2024.
Mitchellcounty as printed
138, 345kV
ONCORutility
2projects listed
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Mitchell, TX: ERCOT queue, 17 active of 19. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Ranger Camp 345/138/69 kV Switch Construct a new 345/138/69 kV Switch to replace existing Morgan Creek Switch ERCOT project 72007 · utility no. R3024 · RPG 23RPG029 |
ONCOR Tier 1 |
Planned Completed tab |
345 | May 2025 actual 2025-04 |
Ranger Camp 345/138 kV Switch to Ranger Camp 345/138 kV Switch Mitchell County |
Ranger Camp 345 |
| Range Rider - Ranger Camp 138 kV Double-Circuit Line Construct a new 138 kV Double-Circuit Line from Range Rider to Ranger Camp Switch. ERCOT project 87861 · utility no. R8722 · RPG 23RPG029 |
ONCOR Tier 1 |
Planned Current-year planned tab |
138 | Oct 2026 | Ranger Camp 345/138 kV Switch to Range Rider 138 kV Switch Mitchell County |
Ranger Camp 345, Range Rider 138 kV Switch |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| June 1, 2026 | 87861 | Projected in-service date | May 2026 → Oct 2026 |
| February 1, 2026 | 87861 | Moved between tabs | Future → Current-year planned |
| October 1, 2025 | 87861 | Moved between tabs | Current-year planned → Future |
| October 1, 2025 | 87861 | Projected in-service date | Dec 2025 → May 2026 |
| June 1, 2025 | 72007 | Moved between tabs | Future → Completed |
| June 1, 2025 | 87861 | Moved between tabs | Future → Current-year planned |
| June 1, 2025 | 87861 | Projected in-service date | Nov 2025 → Dec 2025 |
| February 1, 2025 | 87861 | Projected in-service date | May 2025 → Nov 2025 |
| October 1, 2024 | 72007 | Projected in-service date | Dec 2025 → May 2025 |
| October 1, 2024 | 87861 | First listed | on the Future tab |
| June 1, 2024 | 72007 | Projected in-service date | Dec 2024 → Dec 2025 |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.