Substation Scout

Walleye Creek

Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Milam County. First named in the release with data as of February 1, 2024.

Milamcounty as printed
138, 345kV
ONCORutility
3projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Milam, TX: ERCOT queue, 30 active of 35. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Construct the Voss Lake - Walleye Creek 138 kV Line
ERCOT project 110036 · utility no. R6552
ONCOR
Tier 4
Planned
Future tab
138 Dec 2028 Voss Lake to Walleye Creek
Milam County
Voss Lake, Walleye Creek
Rebuild Austrop Substation (LCRA TSC) - Walleye Creek Switch 345 kV Double Circuit Line
ERCOT project 110334 · utility no. R6569
ONCOR
Tier 3
Conceptual
Future tab
345 Dec 2033 Walleye Creek to Austrop (LCRA TSC)
Milam / Travis County
Walleye Creek, Austrop (LCRA TSC)
Establish Walleye Creek 345/138 kV Switch
ERCOT project 76650 · utility no. R6243 · RPG 23RPG030
ONCOR
Tier 3
In-Service
Completed tab
345 May 2026
actual 2026-05
Walleye Creek to Walleye Creek
Milam County
Walleye Creek

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202676650Moved between tabsCurrent-year planned → Completed
October 1, 202676650Status as reportedPlanned → In-Service
July 13, 2026110036First listedon the Future tab
July 13, 2026110334First listedon the Future tab
June 1, 202676650Projected in-service dateDec 2026 → May 2026
February 1, 202676650Projected in-service dateDec 2025 → Dec 2026
June 1, 202576650Moved between tabsFuture → Current-year planned
October 1, 202476650Projected in-service dateMay 2025 → Dec 2025

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.