Substation Scout

Rosebud

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Milam County. First named in the release with data as of July 13, 2026.

Milamcounty as printed
345kV
ONCORutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Milam, TX: ERCOT queue, 30 active of 35. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Establish Rosebud 345 kV Switch
ERCOT project 110038 · utility no. R6559
ONCOR
Tier 3
Planned
Future tab
345 May 2029 Rosebud to Rosebud
Milam County
Rosebud

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 2026110038First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.