Tidehaven
Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Matagorda County. First named in the release with data as of October 1, 2023.
Matagordacounty as printed
138kV
AEP TCCutility
1projects listed
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Matagorda, TX: ERCOT queue, 23 active of 30. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Tidehaven: Construct New Distribution Station Construct new distribution station on the Blessing to Palacios 69 kV line ERCOT project 71002 · utility no. 3767 DP21X0007 |
AEP TCC Tier 4 |
Planned Future tab |
138 | Nov 2027 | Tidehaven Matagorda County |
Tidehaven |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 71002 | Projected in-service date | Apr 2027 → Nov 2027 |
| June 1, 2026 | 71002 | Moved between tabs | Current-year planned → Future |
| June 1, 2026 | 71002 | Projected in-service date | Sep 2026 → Apr 2027 |
| February 1, 2026 | 71002 | Moved between tabs | Future → Current-year planned |
| February 1, 2026 | 71002 | Projected in-service date | Jun 2026 → Sep 2026 |
| June 1, 2025 | 71002 | Projected in-service date | Apr 2026 → Jun 2026 |
| June 1, 2024 | 71002 | Projected in-service date | Dec 2024 → Apr 2026 |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.
Site Scanner