Substation Scout

Shaula

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Matagorda County. First named in the release with data as of October 1, 2025.

Matagordacounty as printed
345kV
CNPutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Matagorda, TX: ERCOT queue, 23 active of 30. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Facility Ratings Methodology Phase 2 (FRM2) Upgrades
Upgrade Ckt.18 STP to Shaula (Elm Creek) to increase thermal limits as part of FRM2 upgrades.
ERCOT project 99453A
CNP
Tier 4
In-Service
Completed tab
345 May 2026
actual 2026-02
STP to Shaula
Guadalupe / Matagorda County
STP, Shaula

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
June 1, 202699453AMoved between tabsCurrent-year planned → Completed
June 1, 202699453AStatus as reportedPlanned → In-Service
February 1, 202699453AMoved between tabsFuture → Current-year planned
October 1, 202599453AFirst listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.