Sargent

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Matagorda County. First named in the release with data as of February 1, 2025.

Matagordacounty as printed
69kV
STECutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Matagorda, TX: ERCOT queue, 23 active of 30. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Upgrade Sargent - Bay City
Upgrade Sargent - Bay City line to 795ACSR. 2024 RTP; 2025 RTP
ERCOT project 89991
STEC
Tier 4
Planned
Future tab
69 Dec 2027 Sargent to Bay City
Matagorda County
Sargent, Bay City

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
February 1, 202689991Status as reportedConceptual → Planned
February 1, 202689991Projected in-service dateMay 2029 → Dec 2027
February 1, 202589991First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.