Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Matagorda County. First named in the release with data as of July 13, 2026.

Matagordacounty as printed
138kV
AEP TCCutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Matagorda, TX: ERCOT queue, 23 active of 30. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Wadsworth: Retire Station
Retire the Wadsworth station
ERCOT project 109724 · utility no. DP26X0012
AEP TCC
Tier 4
Planned
Future tab
138 Mar 2029 Plotner
Matagorda County
Plotner

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 2026109724Moved between tabsCurrent-year planned → Future
July 13, 2026109724Projected in-service dateMar 2026 → Mar 2029
July 13, 2026109724First listedon the Current-year planned tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.