Substation Scout

Baines Creek 138 kV Switch

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Limestone County. First named in the release with data as of October 1, 2025.

Limestonecounty as printed
138kV
ONCORutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Limestone, TX: ERCOT queue, 9 active of 11. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Establish Baines Creek 138 kV Switch
ERCOT project 99544A · utility no. R6375
ONCOR
Tier 4
Planned
Current-year planned tab
138 Nov 2026 Baines Creek 138 kV Switch to Baines Creek 138 kV Switch
Limestone County
Baines Creek 138 kV Switch

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202699544AFirst listedon the Current-year planned tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this