Sycamore
Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Leon County. First named in the release with data as of July 13, 2026.
Described as new. The quoted wording calls this substation new. “new CTT Sycamore 345 kV station” — project 110324 title, as the utility reported it
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Leon, TX: ERCOT queue, 13 active of 14. Same county, not the same substation.
Location
Leon County, TX
County only. A source prints the county; no point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.
Note: Not the TNMP 'Sycamore Substation' in OpenStreetMap (way 398768864, 69 kV, near 31.475 N, 97.720 W, Coryell/Bell area): different owner, voltage and county. TPIT names neither the line nor the endpoints, so no corridor can be drawn.
Sources: ERCOT TPIT, projects 110324, 110383 (release 39, 2026-10-01). Researched by Substation Scout; checked November 21, 2026.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Add new CTT Sycamore 345 kV station ERCOT project 110324 |
CTT Tier 4 |
Conceptual Future tab |
345 | Dec 2028 | No terminals printed Leon County |
Sycamore |
| Add 210 MVAr cap bank to Sycamore station ERCOT project 110383 |
CTT Tier 4 |
Conceptual Future tab |
345 | Dec 2028 | No terminals printed Leon County |
Sycamore |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| July 13, 2026 | 110324 | First listed | on the Future tab |
| July 13, 2026 | 110383 | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.