Woodard

Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Lamar County. First named in the release with data as of June 1, 2020.

Lamarcounty as printed
345kV
ONCORutility
2projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Lamar, TX: ERCOT queue, 25 active of 28. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Monticello_Paris_Line_Upgrade
Upgrade Monticello - Woodard 345 kV Line
ERCOT project 92852A · utility no. R986 · RPG 25RPG026
ONCOR
Tier 1
Planned
Future tab
345 Dec 2027 Monticello to Woodard
Titus / Lamar County
Monticello, Woodard
Monticello_Paris_Line_Upgrade
Upgrade Woodard - Paris 345 kV Line
ERCOT project 92852B · utility no. R986 · RPG 25RPG026
ONCOR
Tier 1
Planned
Future tab
345 Dec 2028 Woodard to Paris
Lamar County
Woodard, Paris

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
February 1, 202692852AProjected in-service dateDec 2026 → Dec 2027
February 1, 202692852BProjected in-service dateDec 2027 → Dec 2028
June 1, 202592852AFirst listedon the Future tab
June 1, 202592852BFirst listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.