Named in 0 listed projects in ERCOT’s transmission project tracking workbook, in Karnes County, plus 1 on its Cancelled tab. First named in the release with data as of October 1, 2023.

Karnescounty as printed
138kV
AEP TCC/LCRAutility
0projects listed

Projects cancelled. Every project naming Riedel is on the Cancelled tab of ERCOT's workbook.

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Karnes, TX: ERCOT queue, 13 active of 13. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

No projects.

On the Cancelled tab

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Riedel: Build New Distribution Station
Construct new distribution station on the Magnolia Tap to Nixon 138 kV line
ERCOT project 65723 · utility no. 3771
AEP TCC/LCRA
Tier 4
Not reported
Cancelled tab
138 Jun 2025 Riedel
Karnes County
Riedel

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202565723Projected in-service dateJan 2025 → Jun 2025
February 1, 202565723Projected in-service dateAug 2024 → Jan 2025
October 1, 202465723Moved between tabsFuture → Cancelled
October 1, 202465723Projected in-service dateJul 2025 → Aug 2024

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.